OVER 90% OF THE REINFORCED CONCRETE STRUCTURE FOR LONG THÀNH AIRPORT HAS BEEN COMPLETED AFTER NEARLY A YEAR OF CONSTRUCTION

Launched in August 2023, the passenger terminal building, the heart of Long Thành Airport, has made significant strides after nearly a year of construction. The project management board has now commenced construction on the fourth floor, the highest level of the terminal.

The top floor of the Long Thành Airport passenger terminal is currently under construction.

Newtecons and its joint venture partners have implemented a three-shift, four-crew operation to expedite the project timeline. As of late July 2024, the project has achieved a 20% overall completion rate. The reinforced concrete works, in particular, have reached over 90% completion, showcasing the commitment of the Newtecons team to deliver the project on schedule.

Project status in July 2024
Over 90% of the reinforced concrete work on the project has been completed

The mega Long Thành Airport project brings together 10 contractors. Newtecons’ Project Management Board has worked closely with various specialized contractors in civil engineering, steel structure, MEP, BHS, and terminal equipment to ensure smooth construction operations. This close coordination requires Newtecons’ personnel to develop detailed plans and communicate effectively with all relevant parties to provide the highest standards and quality. The achievements are a testament to Newtecons’ ability to integrate, coordinate, and control project progress.

Newtecons is working hand-in-hand with other contractors on the ambitious Long Thành Airport project.

The project faces adverse weather conditions as the southern region enters its rainy season. The muddy site conditions have presented significant challenges regarding site accessibility and material transportation. To mitigate these challenges, the project management board has implemented measures such as providing dedicated transportation for workers and optimizing construction schedules to ensure the project remains on track.

Newtecons’ employee shuttle buses at the construction site

Newtecons has a strong safety culture, demonstrated by its dedication to giving all project staff thorough safety training. A multifaceted approach to safety management is needed for the extensive Long Thành Airport project. This includes weekly safety meetings, daily toolbox talks, and specialized training programs catering to each profession’s unique requirements. These programs have made a big difference in creating a secure and effective work environment.

Regular safety training sessions are held at the project.

The Long Thành Airport project is a testament to Newtecons’ ability to deliver complex infrastructure projects successfully. The company’s proven track record in project management and execution, combined with the collaborative efforts of all stakeholders, has positioned the project for success. This achievement enhances Newtecons’ reputation and contributes to developing a world-class aviation infrastructure in Vietnam.

Newtecons pays meticulous attention to detail, ensuring that all technical standards are strictly adhered to.
Project overview as of July 2024
Project information:

Long Thành International Airport is a national iconic project with a massive construction scope, stringent quality requirements, and tight deadlines. The airport’s passenger terminal, designed as a lotus flower, consists of one ground floor and three upper floors, with a total floor area of 376,451.32 square meters, a roof height of 45.55 meters, and 40 remote aircraft parking stands. Valued at over 35,000 billion VND, with a construction period of 39 months, this is one of the largest and most complex contracts to date. In the first phase, Long Thành Airport will have a capacity to serve 25 million passengers and 1.2 million tons of cargo per year. Upon full completion, the airport will feature four runways, four passenger terminals, and supporting facilities, with a capacity of 100 million passengers and 5 million tons of cargo annually.

Share

Related article

25, 05, 2025

KICKSTARTING THE FINISHING PHASE OF DANANG’S ICONIC COASTAL PROJECT

12, 05, 2025

TOPPING-OUT CEREMONY FOR TOWER D12 OF THE LUMIÈRE PROJECT IN HANOI

12, 05, 2025

COMMENCEMENT OF ROUTE INN HAI PHONG 5-STAR HOTEL PROJECT – A KEY PROJECT TO CELEBRATE THE 70TH ANNIVERSARY OF THE LIBERATION OF THE CITY

05, 05, 2025

NEWTECONS SPREADS SAFETY CULTURE AT “SAFETY DAY 2025” HOSTED BY CAPITALAND DEVELOPMENT (VIETNAM)